AFJV CTP CBE Carousel Demobilisation
March - November 2022
All Industries Engineering completed the mechanical and structural installation of CBE Group’s automated precast carousel for the Acciona–Ferrovial Joint Venture. The precast facility was established to support production of tunnel lining segments for the Central Tunnelling Package of the Sydney Metro West project.
The scope of works was delivered in accordance with CBE Group’s issued engineering drawings and design documentation, including the installation of carousel equipment, structural steelwork, and associated mechanical assemblies.